The combination of OBT and LSMW approach was chosen to ensure full integration of logistics and financial data. In addition, it was important for Landis+Gyr to harmonise and convert the chart of accounts during the transformation.
Around 350 business objects and 700 tables were transferred from SAP ERP. The largest table transferred had about 25.5 GB. Three test cycles were carried out over a period of four months, during which the current master and transaction data from the production system was constantly retested - resulting in continuous process improvements between the individual cycles.
The technical downtime was less than 48 hours and was planned over a holiday weekend, starting with the system backup and OBT changeover and ending with the final reconciliation activities. The overall benefit for the company was the minimal risk and a short time frame - the project was completed on time and as planned.
The migration manager of GAMBIT Consulting GmbH, Jochen Knösels, explained: "The trustful and cooperative cooperation between GAMBIT Consulting GmbH and the DM< teams helped us to realize the short project time for this demanding project".
"Simplifying all our ERP system landscapes helps us to improve business processes," said Sascha Merz, CIO for EMEA and head of global ERP systems at Landis+Gyr. "This will lead to leaner processes and more transparency in our supply chain and accounting".